To set a baseline:
1. In the ribbon on the Project tab, within the Schedule group of commands, click set baseline -> set baseline.
2. Making sure Set Baseline and Entire Project are set, clicking OK sets the Baseline.
3. Notice as the baseline is now set the values of the start, finish, baseline start and baseline finish columns are now the same.