Exam Prep 70-632 - Configuring Project 2007

Remove information from file properties on save Tools -> Options -> Remove information from file properties removed the author’s, manager’s and company name and last save information. This option is not selected by default and only applies to the project open when this option is selected.

Tracking resources overtime work
Adding the actual overtime work field to the resource usage view allows tracking of the amount of overtime worked by resources in project.

Tracking actual progress
Actual progress is tracked by indicating the percent of completed task (% complete) field. When this field is updated the values for actual duration and remaining duration are automatically updated.

Changing the timescale in current view
Clearing the use fiscal year settings in the timescale box only changes the settings for the current view. To change the settings for all views configure the settings via Options -> Calendar.

The View Table: Schedule
Shows start, finish, late start, late finish, free slack and total slack.